Gladstone Court

Client: Stevenage Borough Council
Value: £600k

Brief
 

Gladstone Court is a sheltered residential accommodation  6 storey building consisting of 43 flats, communal lounges and offices. The existing heating and hot water services are provided by a centralised plant room at ground floor level.

The brief was to modify and update the existing boiler room and controls, design and install new heating and domestic distribution pipework services installed in all corridor ceilings to serve new JAGA LST radiators in all flats and communal areas.

Challenges
 

  • An demanding installation programme to complete all works in a 12 week programme including a 1 week LST heating installation programme to all 43 occupied flats.
  • A 2 week in house design produced for client approval prior to the 12 week installation programme.
  • Maintaining all heating and domestic services to all areas during the change-over period.
  • Venerable residents requirements during the internal heating works, including de-canting and carer provisions.
  • Maintaining a safe working environment while labour intensive works are to be carried out.

Solutions | Outcome
 

  • Full in-depth planning and RLO Consultations with all residents and venerable residents to ascertain their individual requirements and needs during the installation works.
  • Prior detailed planning of all installation works with client, scheme managers, site managers and all residents to ensure an understanding of the project and programme with all concerned.
  • Phased programming of internal installations to suit resident requirements.

Outcome:

  •  A very demanding and labour intensive programme delivered on time and on budget with minimal disruption to all residents. Considering this project was completed during September – December 2013 during the cold season, it was an excellent achievement by all to complete this project while maintaining constant heating and hot water to all areas of the building

Mechanical & Engineering Gallery

Example
Thoroughly professional job, on time and on budget.  End Quote
Dave Royce, Wates Construction
Chameleon

Introduction

Formed in 1993, Stapletech has become one of the leading specialist contractors in the South East.  Services provided to both private and public sector clients include Mechanical, Electrical (Domestic & Commercial) and more recently 'new technologies' including Solar Thermal and award winning Eco Home retrofits.  Our highly skilled engineers complete planned, preventative & responsive maintenance and undertake Legionella Testing and Compliance.  We are proud to have such a fantastic team who ensure at all times that our clients receive a quailty of service that they can rely upon.

LEARN MORE

Testimonials

  • Stapletech are an excellent, reliable and efficient contractor. J. Murray,
    Project Quantity Surveyor Modern Housing Solutions
  • 19 residents have completed KPI questionnaires with maximum marks across the board. Keep up the good work! Mervyn Brown,
    Ig9 Consultant Project Managers
  • Extremely competent contractor, fully managed all Client expectations from inception to completion. Lee Yeates,
    Project Manager Keepmoat